12
4. Inspect side load strips (24) for tightness in base and signs of wear. Side strips should be replaced
when depth of wear exceeds 0.003 inch.
5. Inspect link retaining pins (47) for tightness in base and signs of wear.
6. At bottom of base assembly, check load strips (19) for tightness in base and signs of wear. Load strips
should be replaced when depth of wear exceeds 0.003 inch.
7. Using a torque wrench, tighten diaphragm retaining screws (46) to 50 inch-pounds.
8. Inspect behind diaphragm bead (27) for loose particles.
9. Inspect the nine link pivots (13) for flat spots.
10. Inspect piston load strips (18) and (19) for signs of unusual wear and resilient retainer (17) for fit.
11. Inspect piston (14) for nicks or burrs.
12. Inspect all load strip rollers (20) for straightness and flat spots.
13. Inspect all electrical connections for corrosion.
3.9 Lubrication
Prior to assembly, all unplated steel parts should be coated with grease or some rust-inhibiting agent. Side
buttons and load strip assemblies must be packed with Shell Darina AX or an equivalent extreme-pressure
grease.
3.10 Reassembly
After all parts have been cleaned and inspected, the weigher can be reassembled.
3.11 Installing the PC Board
Position the PC Board in the weigher and secure using the four screws (61). Connect the cables as shown with
the exception of the display connector.
3.12 Reassembling the Display Cover
The metal mating surfaces around the display cover and the base assembly must be sealed for environmental
protection. Reconnect the display cable. Place the display cover in position and install the holding screws
(50). After tightening the screws, place a small amount of silicone over the screw heads. Apply a thin film of
RTV silicone rubber compound around all mating surfaces.
3.13 Reassembling Links
Use the following procedure to reassemble the links. See Figure 5 on page 16 for location of numbered parts.
1. Replace the link bushings (15) into links (9) and (10) so that the small hole of bushing faces the
bottom of base assembly.
2. Pack grease into the piston load strip assembly (16) and the chamfered corners of the upper strip (18)
to the piston top.
3. Grease upper and lower link bearings (13).
4. Place links over retaining pins (47).
Note: Links must be returned to original position.
Vue de la page 13